What do you call the time a task can be delayed without affecting the next task?

Prepare for the Edexcel AS/A‑Level Business Theme 3 Exam. Engage with multiple choice questions and detailed explanations. Enhance your understanding and get exam ready with our comprehensive resources!

The correct answer is 'Free float.' Free float refers to the amount of time that a task can be delayed without affecting the start of any subsequent tasks. This concept is crucial in project management as it helps in scheduling and resource allocation. By understanding free float, project managers can identify which tasks have some flexibility in their schedule, allowing them to optimize overall project timelines and efficiently manage resources.

In contrast, total float indicates the total time a task can be delayed without impacting the overall project completion date, rather than just the tasks that follow it directly. Latest finish time refers to the latest point in time a particular task can be completed without delaying the subsequent task or the project as a whole. Critical path, on the other hand, is the sequence of stages determining the minimum time needed for an operation in project management, highlighting the tasks that are essential for timely project completion. A clear differentiation between these terms is essential for effective project planning and management.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy